Northeast U.S. Based Utility

When an electric utility client in the Northeast U.S. requests assistance with a short term hazard tree program, DRG has staff en route within six hours and exceeds client expectations in the work performed.

The Challenge

Utility line tree trimming typically occurs in cycles of 3-5 years. However, conditions in the landscape are continually subject to change within those cycles. Storms, disease, insect infestations, construction, and/or other events can potentially create tree hazards that demand attention between scheduled tree trimming operations.

In September 2018, the electric utility identified potential tree hazards across their system. The decision was made for immediate assessment and remediation.

The Solution

Based on an existing relationship with Davey Resource Group, the utility immediately reached out to DRG for assistance with their short term hazard tree program, requesting staff to identify and assess hazard trees.

Within 6 hours, DRG identified and mobilized the appropriate individuals to staff the team. In addition to staff members already on site, DRG called in qualified individuals from Massachusetts and North Carolina and had them mobilized to the site.

Over the next four weeks, DRG staff identified and assessed all hazard trees in the client’s grid. The DRG team’s technical expertise allowed them to quickly adapt and utilize the client’s own collection software to collect tree data, eliminating the need to sync or convert data.

The Results

DRG commenced work on the project on Tuesday, September 18. The utility’s initial deadline for completion was set for the end of December; however, the DRG team completed the 310 line mile project to the client’s satisfaction on Wednesday, October 17, about 10 weeks ahead of schedule.

>> Contact us to learn more about Davey's Utility Solutions

Related Client Work

Utility Banner3
Electric Investor-Owned Utility

Strategic Planning Yields 250% Distribution Mile Completion Increase For Teco

Davey comes to the rescue when Tampa Electric needs additional staff to trim more than the usual number of miles along its distribution lines.
Read More
Entergy Storm Response Binghampton 3
Electric Investor-Owned Utility

DRG Performs Extensive Post-Storm Work After Hurricane Ida

DRG crews have been on the Gulf Coast since August 2021 helping a Southeast U.S. utility restore its distribution system after Hurricane Ida devastation.
Read More
Two Employees
Two Employees

Get In Touch With Us!

We pride ourselves at Davey Tree on providing prompt, professional and personalized service from certified arborists that live, work and engage in your community. Contact one of our Davey Tree specialists for your residential, commercial, utility, or environmental needs.

Let's Find What
You're Looking For!